Non-Compliance detail


  
Summary
 
Licence number: 766
Annual Return Start: 01 Jan 2007
Annual Return End: 31 Dec 2007
Date Received: 28 Feb 2008
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2.1 The sampling plane locations in the boiler ductwork at Wallerawang power station do not satisfy sample methodology of AS4323.1-1995. Appropriate Action taken by licensee 1
L4.1 Uncontrolled discharge into Neubecks Creek from Mount Piper cooling tower #1 following blockage of filter screens. Appropriate Action taken by licensee 1
L3.1 Minor exceedance of pH at LDP1, and TSS at LDP3 . Appropriate Action taken by licensee 2