Licence conditions for pollution studies and reduction program


  

Licence conditions for pollution studies and reduction programs

Summary
 
Licence number: 528
Title: Erosion and Sediment Control Short Term Action Plan
Start date: 14 Oct 2016
 
Licence Condition
The licensee must undertake works in the Western Outlier, Southern Outlier, Southern Open Cut Extension and Stony Creek areas of the premises as listed in the table below by the associated completion date:
The licensee must undertake works in the Haul Road from Southern Open Cut to Western Outlier area of the premises as listed in the table below by the associated completion date:
The licensee must undertake works in the Southern Open Cut area of the premises as listed in the table below by the associated completion date:
The licensee must undertake works in the 8 Trunk Open Cut area of the premises as listed in the table below by the associated due date:
The licensee must undertake works in the Haystack Open Cut area of the premises as listed in the table below by the associated completion date:
The licensee must undertake works in the 2/3 Trunk areas of the premises as listed in the table below by the associated completion date: