Environmental Issues
Public registers
POEO Public Register
Licences, applications and notices search
Penalty notices search
Enforceable undertakings search
Enforceable undertakings media releases
Exemptions and approvals search
Prosecutions or civil proceedings search
Terms of use: POEO public register
Licensing FAQs
List of licences
Unlicensed premises regulated by the EPA
Contaminated land record of notices
About the record of notices
List of notified sites
Tips for searching
Disclaimer
Dangerous goods licences
Pesticide licences
Radiation licences
Home
Public registers
POEO Public Register
Licences, applications and notices search
Non-Compliance detail
Summary
Licence number:
467
Annual Return Start:
01 Jan 2009
Annual Return End:
31 Dec 2009
Date Received:
02 Mar 2010
Licence Condition number
Type of non-compliance
EPA actions
No. of times occurred
L3.1
Total suspended solids exceeded at LDP001 (x 3 - minor exceedances), LDP2 (x 2 - maximum of 111 mg/L ) & LDP3 (x 1 at 320 mg/L).
EPA has written to licensee regarding non-compliance and relevant action
1
M6.1
The volume of liquids discharged to water was not monitored for 24 days due to datalogger failure at LDP002. Temporary flow meter with data logger installed until New Monitoring Station complete.
Appropriate Action taken by licensee
1
M2.1
PM10 and TSP sampling not collected to time frame due to misinterpretation of licence condition. Measurments were collected over a 24 hour range rather than 6 day. Since corrected by licensee
EPA to monitor future compliance with this condition
1
O1.1
Pumping to the utilisation area from the sewage oxidation lagoons has not been carried out due to failure of the pumping system. Resulted in minor overflows at times of heavy rain.
Appropriate Action taken by licensee
1
A2.1
Minor exceedance of total coal mined during the 2009 reporting period due to the cyclical nature of longwall mining (3.69 Mtpa mined versus a licence scale limit of 3.5 Mtpa). No environmental impact.
Appropriate Action taken by licensee
1
M2.1
Failure to monitor surface water discharges at LDP3 on three occassions due to short duration of rain event and resultant discharge., and data logger not fitted with telemetry function to warn licensee of impending overflow.
Appropriate Action taken by licensee
1