Title: Complete Permanent Clean Water Diversion works
Start date: 19 Jul 2021
 
Licence Condition
U2.1 The Licensee must complete all permanent upslope diversion drainage at the premises as follows: A)  SECTION F (CH2000 – 2300)         ·  Westbound by 31/07/23 B)  SECTION G (CH2300 – 3200)         ·  Eastbound by 29/09/23
The Licensee must advise on the progress of the permanent clean water diversion works in each monthly compliance report required under condition O4.14.
The Licensee must submit a signed statement from the Project Manager to the EPA to confirm the completion of the permanent clean water diversion works within 5 business days of works being completed.