Environmental Issues

Environment protection licences

Non-Compliance detail


  
Summary
 
Licence number: 20971
Annual Return Start: 28 Sep 2017
Annual Return End: 27 Sep 2018
Date Received: 26 Nov 2018
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
L2.1 During dewatering of a sediment tank turbid water was observed in the gutter on Castlereagh street adjacent to the Pitt street north site. the dewatering pump was immediately switched off and clean up commenced. N/A N/A
L4.5 On the 18 June 2018 high noise impact works were carried out at the Sydney Metro Crows Nest site during the agreed respite periods N/A N/A
O3.1 During a Environmental Representative inspection dust was observed passing through louvres on the northern side of the acoustic shed on the corner of berry st and Miller street N Sydney N/A N/A
L4.14(j) Out of hours work were being undertaken These works were assessed to be within background noise plus 5dB(A). A review of work activities identified that the work was above background noise levels which resulted in a breach of respite periods N/A N/A