Non-Compliance detail


  
Summary
 
Licence number: 12894
Annual Return Start: 07 Jul 2024
Annual Return End: 06 Jul 2025
Date Received: 04 Sep 2025
 
Licence Condition numberType of non-complianceEPA actionsNo. of times occurred
M2.2 – Monitoring Po Failure to continuously monitor PM10 concentration at Monitoring Point 19 due to breakdowns and maintenance. EPA action determined as part of scheduled inspection program 19
M2.2 – Monitoring Po Failure to continuously monitor PM10 concentration at Monitoring Point 20 due to breakdowns and maintenance. EPA action determined as part of scheduled inspection program 14
M4.1 – Monitoring Po Failure to continuously monitor meteorological parameters at Monitoring Point 5 due to technical faults, routine maintenance and reasons outside foreseeable control of Mangoola Coal Operations. EPA action determined as part of scheduled inspection program 64
M4.1 – Monitoring Po Failure to continuously monitor meteorological parameters at Monitoring Point 18 due to technical faults, routine maintenance and reasons outside foreseeable control of Mangoola Coal Operations. EPA action determined as part of scheduled inspection program 59